DESCRIPTION:
Playpave Sporting Surface
Systems provide a highly durable, all weather sporting surface with
excellent abrasion resistance and uniform texture.
Manufactured from selected premium 100% acrylic resins, light stable oxide
pigments and proven reinforcing powders assure maximum U.V. resistance to
provide years of non-fade life.
The specialised resins used in the production of Playpave provide
excellent scuff resistance in both wet and dry conditions.
The Playpave surface system for asphalt bases comprises two (2)
applications of Filler Coat and at least one (1) application of Playpave
Top Coat.
Ball bounce on Playpave is completely true and ball speed can be varied by
the application technique of the qualified contractor.
ADVANTAGES:
Early water resistance.
Dries rapidly. Excellent adhesion. Excellent scuff resistance (in wet and
dry). Provides positive traction. Is easily cleaned. Remains flexible.
Provides true ball bounce and controlled ball speed.
TYPICAL USES:
Tennis Courts, Basketball
Courts, Outdoor Play Areas, Volleyball Courts, Multi-purpose Sport Courts.
SURFACE PREPARATION:
NEW ASPHALT SURFACES
- A tight, uniform and even surface is required to avoid the need for
additional applications of Filler Coat. New asphalt surfaces shall be
allowed to cure for a minimum of 10 days before the application of the
Playpave System. The surface finish shall be thoroughly cleaned to remove
all loose dirt, dust, oil, grease, leaves and other debris. The surface
shall be flooded with water to check for low areas. Minor depressions up
to 3mm may be leveled using undiluted Filler Coat applied by steel
trowel/squeegee or a combination of both. Deeper depressions and minor
surface cracks shall be filled with Resurfacer blend. Refer technical data
sheet on Resurfacer for further details.
PREVIOUSLY COATED
ASPHALT SURFACES - Surface preparation requirements are similar to
those stated above for new asphalt. The surface Shall be thoroughly
cleaned and leveled. Existing cracks shall be cleaned and filled with
Flexi-Fill. Existing line markings applied using an oil-based paint shall
be removed.
APPLICATION:
Do not use Playpave when
temperatures are either below 10°C or above 35°C, or when rain is
imminent. Sound surfaces require the use of two (2) coats of Filler Coat
and one (1) coat of Playpave Top Coat. Areas of excessive porosity should
receive an additional coat of undiluted Filler Coat applied by squeegee or
trowel. In general, unless a slower playing field for tennis is required,
the first coat is to be applied in a perpendicular (length wise) direction
to the playing net. The second coat is applied parallel with the playing
net with the finish coat perpendicular (length wise). To create a slower
playing field the reverse procedure is applicable.
BASE COATS -
Dilute Filler Coat in the ratio of 4 parts filler coat to 1 part clean
water. Stir the mixture thoroughly before an during the application
procedure to provide a homogenous blend and avoid settlement. Pour the
mixture in 'wind rows' over the surface and spread evenly with a wide
flexible rubber squeegee, generally 600mm to 900mm in width. Level off
with a second squeegee. Note: In situations where the asphalt base is
unusually porous and additional filling is required, it may be necessary
to apply additional coats of Filler Coat neat without dilution. Any
subsequent squeegee lines must be rubbed smooth prior to the application
of the final Filler Coat.
SECOND COAT (OR FINAL
FILLER COAT) - Dilute Filler Coat in the ratio of 3 parts to 1 part of
clean water and repeat as for the first coat
TOP COAT - It is
important that all ridges are leveled off prior to the application of the
finish coat and that the finish coat is true with an even texture. Dilute
Playpave in the ratio of 3 parts Playpave to 1 part clean water. Pour the
mixture in 'wind rows' over the surface and spread evenly with a wide
flexible rubber squeegee, level off with a wide firm bristle broom before
coating starts to dry. Apply a minimum of 1 coat, length wise of the
court. Should a smoother finish be required, the top coat may be finished
by squeegee alone, however the dilution should be changed to 4 parts
Playpave to 1 part clean water.
COVERAGE: (BASED ON
UNDILUTED MATERIAL)
Coverage will depend upon
the texture of the base surface to which the Playpave Filler Coat is
applied.
| PLAYPAVE FILLER COAT |
|
|
1st coat: |
2-3 sqm per litre |
|
2nd coat: |
3-4 sqm per litre |
| PLAYPAVE TOP COAT |
3-4 sqm per litre |
DRYING TIMES:
In general the first
filler coat application will take longer to dry because of the extra
thickness of the product due to voids.
Allow approx. 1-1.5 hours at 25ºC. Additional coats average 0.5 - 1 hour
at 25ºC.
Allow a minimum of 1 hour, depending on temperature, between coats.
There is no maximum drying time limit between re-coats.
Playing time is generally 24 hours after completion, dependant on good
drying conditions.
Full hardness and abrasion resistance will take 4 -5 days under good
drying conditions.
LINE MARKING:
Apply A.P. Line Marking
Paint by brush, roller or spray. Colours available are white, yellow, red,
blue, black and orange. Apply in two (2) coats by brush or roller or one
(1) coat by an appropriate spraying unit to achieve a total coverage of
approximately 70 lineal metres per litre for 50mm wide lines.
COLOUR RANGE:
Playpave is available in
nine (9) standard weather resistant colours. Special colours are available
on request. Deep Green, Forest Green, Light Sage, Terracotta, Light
Terracotta, Mid Tan, Mid Blue, Blue Grey, Fawn.
PRECAUTION:
Store in a cool place,
never in the hot sun, keep material from freezing. Clean all equipment
with water, immediately after use. Do not allow Playpave to drip on
adjacent surfaces. Immediately remove drips with water as dried product is
difficult to remove and will create a blemish on the finished surface.
LIMITATIONS:
Although Playpave has
excellent early water resistance, do not apply when rain is imminent or
temperatures are below 10°C or above 35°C.
|