DESCRIPTION:
The Attack 2000 system has been purpose
designed and formulated to provide a highly durable, all weather-sporting
surface with maximum skid resistance. Manufactured from selected premium
100% acrylic resins, light stable oxide pigments, and a unique combination
of reinforcing powders and aggregates to proovide durability and
performance. The specialised resins used in the production of Attack 2000
provide excellent scuff resistance in both wet and dry conditions.
ADVANTAGES:
Provides maximum traction. Early water
resistance. Dries rapidly. Excellent adhesion. Excellent scuff resistance
in wet and dry conditions.
SURFACE PREPARATION:
New concrete shall be wood float or broom
finished. DO NOT USE HARDENERS OR DRYERS. ACCELERATORS BASED ON CALCIUM
CHLORIDE SHOULD NOT BE USED IN THE CONCRETE MIX.
Technical information guidelines on base construction, design and general
information on base repairs and preparation are provided under the heading
'Foundations, Bases and Soils'.
If a curing membrane is to be used, use only those approved by the
manufacturer, Adcrete Industries Pty Ltd.
Allow concrete to fully cure.
Curing times can vary from 14 to 28 days dependant upon climatic
conditions and the strength of the concrete mix.
All surfaces must be clean, dry and free of grease, oil, laitance, curing
compounds other than those recommended by the manufacturer, forum release
agents and any other contaminants which may impair adhesion of the sealer
or base coat.
Remove any residual paint with paint stripper, scraping, grinding or sand
blasting to achieve clean concrete surface.
Remove any loose or spalled concrete down to a clean sound surface.
Hairline and minor non-structural cracks should be veed out and filled
with a high performance solvent free elastomenic sealant compatible with
the system.
Make good all depressions, spalled areas, bird baths, etc., with a blend
of sand, cement and Super M (refer Super M data sheet).
ACID ETCHING:
Ref: Surface Preparation of Concrete, data
sheet SP-C. New or old concrete surfaces must be etched with a solution of
1 part Hydrochloric Acid to 3 parts water. On porous surfaces the mix
ratio can be reduced to 1:3.
Do not allow acid mixture to dry, keep the surface area damp. Allow to
react for approximately 10 to 15 minutes, scrubbing the mixture thoroughly
with a stiff bristle broom.
Rinse off with copious quantities of clean water applied at high pressure
to remove all traces of concrete salts and allow the surface to dry.
If white residues of concrete salts are evident on the dried surface,
remove by scrubbing, high pressure hosing and a very diluted acid wash (10
to 1), if necessary until the surface is clean.
APPLICATION:
Do not use Playpave when temperatures are
either below 10°C or above 35°C, or when rain is imminent.
THE SYSTEM:
Sound surfaces normally require the use of
one (1) application of Concrete Sealer, and one (1) application of Base
Coat and one (1) application Top Coat. Areas of excessive porosity should
receive additional treatment. Following the application of the Concrete
Sealer it may be necessary to apply an application of undiluted or
partially diluted Base Coat, apply by squeegee or trowel.
Alternatively apply an application of a blend of Super M, sand and cement
prior to the installation of Concrete Sealer.
SEALER COAT:
Dilute Concrete Sealer in the ratio of 2
parts sealer to 1 part clean water.
Stir the mixture thoroughly before and during the application procedure to
provide a homogenous blend.
Paint around the edges and posts with a paintbrush.
General application may be by brush, roller, airless spray or a
combination of squeegee and short nap roller, never by squeegee
only.
Note: After the Concrete Sealer has dried, inspect the surface for
irregularities and obvious low spots.
Minor depressions and surface irregularities may be leveled using a blend
of Super M, sand and cement.
Allow a minimum of 2 hours between coats.
Any subsequent trowel or brush lines must be rubbed smooth prior to the
application of the Base and Top Coats.
BASE AND TOP COATS:
Dilute product in the ratio of 3 parts to 1
part clean water.
Stir the mixture thoroughly before and during the application procedure to
provide a homogenous blend and avoid settlement.
Pour the mixture in "wind rows" over the surface and spread
evenly with a wide flexible rubber squeegee, level off with a wide firm
bristle broom before coating starts to dry.
Apply a minimum of 2 coats.
Apply the Base Coat crosswise of the court with the Top Coat application
lengthwise of the court.
It is important that all ridges are leveled off prior to the application
of the finish coat and that the final coat is true with an even
texture.
COVERAGE: (BASED ON UNDILUTED
MATERIAL)
Coverage will depend upon the texture of
the base surface to which the Top Coat is applied.
| CONCRETE SEALER |
8.5 sqm per litre |
| BASE COAT |
3.5 sqm per litre per coat |
| TOP COAT |
1.75 sqm per litre per
coat |
DRYING TIMES:
In general the first filler coat
application will take longer to dry because of the extra thickness of the
product due to voids.
Allow approx. 1-1.5 hours at 25ºC. Additional coats average 0.5 - 1 hour
at 25ºC.
Allow a minimum of 1 hour, depending on temperature, between coats.
There is no maximum drying time limit between re-coats.
Playing time is generally 24 hours after completion, dependant on good
drying conditions.
Full hardness and abrasion resistance will take 4 -5 days under good
drying conditions.
LINE MARKING:
Apply A.P. Line Marking Paint by brush,
roller or spray.
Colours available are white, yellow, red, blue, black and orange.
Apply in two (2) coats by brush or roller or one (1) coat by an
appropriate spraying unit to achieve a total coverage of approximately 50
lineal metres per litre for 50mm wide lines.
COLOUR RANGE:
Playpave is available in nine (9) standard
weather resistant colours. Special colours are available on request. Deep
Green, Forest Green, Light Sage, Terracotta, Light Terracotta, Mid Tan,
Mid Blue, Blue Grey, Fawn.
PRECAUTION:
Store in a cool place, never in the hot
sun, keep material from freezing. Clean all equipment with water,
immediately after use. Do not allow the product to drip on adjacent
surfaces. Immediately remove drips with water as dried product is
difficult to remove and will create a blemish on the finished
surface.
LIMITATIONS:
Although the product has excellent early
water resistance, do not apply when rain is imminent or temperatures are
below 10°C or above 35°C.
|